Inside a Royalwoods Fit-Out: From Shop Drawings to Reveal

Clients often ask what the twelve weeks of a typical project actually contain. Here is the honest breakdown.
Weeks 1–2: Survey and set-out
We laser-survey every room and draw each elevation. You approve the panel composition on paper — moving a stile on a drawing is free; moving it on a wall is not.
Weeks 3–6: Workshop fabrication
Mouldings are milled, panels assembled and everything primed in our workshop while your home stays untouched.
Weeks 7–10: Installation
The site crew fixes, scribes and caulks. Services — sockets, switches, AV — are coordinated so nothing interrupts a panel face.
Weeks 11–12: Decoration and reveal
Final sprayed topcoats, snagging under raking light, and handover. We photograph every project on completion — most of what you see on this site is our own documentation, not renders.
Keep Reading
CraftCurved Stone: Setting Travertine Around a Bay WindowCladding a flat wall in travertine is a day's work. Wrapping a curve — around curved glass, with the joints still reading true — is the detail that separates a stonemason from a tiler.Design NotesWhat a Walk-in Closet Actually Needs (Beyond Hanging Rails)Most walk-in closets fail for the same three reasons: wrong rail heights, no drawer strategy, and lighting added as an afterthought. A designer's checklist before you commit to a layout.